Template 26Stage 7 · SustainPowerPoint · Excel · PDF

Strategy ExecutionOperating Model Transformation

Benefits Realisation Tracker

Map how the programme creates value, give every benefit an owner, a measure and a date, and track it until it is real.

Time2 hours to set up, then monthlyForProgramme managers, finance partners, sponsors
Download free

What it is

A benefits kit from plan to proof. The benefits map links outputs to capabilities, outcomes and strategic objectives. The register gives every benefit an owner, a measure, a baseline and a target date. The Excel tracker compares planned and actual benefits over time and summarises progress for the steering committee.

Why use it

Programmes are funded on the benefits they promise, but they are usually closed when delivery finishes. Without owners, baselines and tracking, nobody can say whether the investment paid off. A simple register and a regular review keep the promised value in view.

How to use it

  1. Draw the benefits map from right to left: start with the objectives, then the benefits, the changes in how people work, and the enablers.
  2. Give each benefit an owner in the business, a measure, a baseline and a target date.
  3. Set baselines before the change starts.
  4. Enter actual results each quarter in the Excel tracker and compare them with the plan.
  5. Keep tracking after the programme closes. Many benefits arrive months after go-live.

When it helps

  • Writing or refreshing a business case
  • Mobilising a programme, to agree owners and measures
  • Reporting progress to a board or investment committee
  • Reviewing value after go-live

What is inside

  • A guide to benefits management and measures that work
  • A benefits map from outputs to objectives
  • A benefits register with owners, baselines and dates
  • An Excel tracker for planned versus actual benefits

Worked example

Running example · a fictional UK lenderWhat the mortgage programme has to deliver

Four benefits from the register, each owned outside the programme team.

Time to decisionBaseline 21 days, target 7 days by the end of year one. Owner: head of mortgage operations.
Manual checking time per caseBaseline 3.4 hours, target 1 hour. Owner: head of underwriting.
Share of broker mortgagesBaseline 2.1%, target 2.6%. Owner: sales director.
Cost-to-incomeBaseline 66%, target below 58% by 2028. Owner: finance director.
Quarter 2 position11 days to a decision, on track. 1.6 hours of checking, on track. Broker share 2.2%, at risk.

What happened next. Broker share lagged because brokers did not yet trust the faster times, which became the focus of the next quarter's OKRs.

Preview

Benefits Realisation Tracker template, page 1
Page 1 of 3 · click to enlarge
Benefits Realisation Tracker template, page 2
Page 2 of 3 · click to enlarge
Benefits Realisation Tracker template, page 3
Page 3 of 3 · click to enlarge

Questions

Who should own a benefit?

A named person in the business who will be there when the benefit is due, not the programme team. The owner must have the authority to make the change stick.

When should you start tracking benefits?

Set baselines before the change starts, then track from the first release. Many benefits arrive months after go-live, so keep tracking after the programme closes.

Related readingBenefits don't realise themselvesMost programmes stop measuring at go-live, which is exactly when the benefits are meant to start. Someone has to own them after the project team has gone.

Rate and review

How useful was this template?

Your rating and comments help me improve the template and decide what to build next. It takes less than a minute.

Your rating

The Inflexion Note

No schedule. Just a note when I learn something worth your time.

One idea, one free resource and one thing to try. If I have nothing useful to say, you will not hear from me. Unsubscribe with one click.

I will only use your email to send the Note.