Steering Committee Pack
A short, decision-focused pack with status on a page, the decisions needed and the actions agreed.
Where it fitsStage 6 of 7 · Deliver: How do we bring people with us?
What it is
A four-page steering committee pack with a guide. Status on a page gives the overall RAG and status by scope, schedule, cost and benefits. The decisions page sets out each decision with options, a recommendation and its impact. The log records every action and decision agreed, with owners and dates.
Why use it
Many steering committees spend an hour reading status and five minutes deciding. A pack built around decisions changes the conversation, and makes the committee earn its place in the governance.
How to use it
- Send the pack at least two working days before the meeting.
- Lead with status on a page: overall RAG, the status of scope, schedule, cost and benefits, and a two-line summary.
- Set out each decision needed, with the options, a recommendation and the impact.
- Read back the actions and decisions before the meeting closes, and record them in the log.
- Keep detail in the appendix, so the meeting spends its time deciding.
When it helps
- Monthly or fortnightly steering committee meetings
- Programme board or sponsor updates
- Resetting a steering committee that has become a reporting forum
- Escalating a decision that is stuck
What is inside
- A guide to running a decision-focused steering committee
- Status on a page with RAG by dimension
- A decisions and escalations page with options and recommendations
- An actions and decisions log
Worked example
One page of status and one decision, from the month the accuracy test came back.
| Overall status | Amber. Payslip reading is ahead of target, but bank statement accuracy is 88% against a target of 95%. |
|---|---|
| Decision needed | Should we use open banking data for income instead of reading bank statements? |
| Options | Keep manual checks for bank statements: no extra cost, but only half the time saving. Switch to open banking: £80k and six weeks, full saving. |
| Recommendation | Switch to open banking, funded from contingency. |
| Decision recorded | Approved. Owner: programme director. The RAID log and business case are updated. |
What happened next. The decision took 15 minutes, because the pack set out the options and the recommendation clearly.
Preview
Questions
What should a steering committee pack include?
Status on a page, the decisions the committee needs to make, and the actions and decisions agreed. Top risks can come from the RAID log. Anything else belongs in an appendix.
How long should a steerco pack be?
Short. Four or five pages is enough for most meetings. Lead with the decisions, so the committee spends its time deciding rather than reading status updates.
Rate and review
How useful was this template?
Your rating and comments help me improve the template and decide what to build next. It takes less than a minute.
Thank you.
Your feedback has been sent. If you have got another minute, share the template with someone who'd find it useful.