RACI & Governance Pack
Make it clear who decides, who does the work and how issues travel, before the first argument about it.
Where it fitsStage 5 of 7 · Mobilise: Who does what, and how do we stay in control?
What it is
A governance kit for a programme or change. The guide explains RACI and the rules that keep it useful. A governance page sets out the tiers, from board to workstreams, with their purpose, members and rhythm. The Excel RACI covers activities and roles and flags any row without exactly one accountable person.
Why use it
Unclear decision rights are one of the quietest reasons programmes slow down. Deciding who decides, before the hard decisions arrive, saves weeks of escalation and stops the same debate happening three times.
How to use it
- List the key activities and decisions down the side, and the roles across the top. Rename the roles to fit.
- Mark each cell R, A, C or I. Every row needs exactly one A.
- Use the Excel version, which flags any row with no A or more than one.
- Set out the governance forums: purpose, chair, members, how often they meet and what each one decides.
- Agree the escalation limits, so people know which decisions they can make without asking.
When it helps
- Mobilising a new programme or project
- Fixing slow or contested decisions in an existing programme
- Setting up a steering committee and terms of reference
- Clarifying roles after a reorganisation
What is inside
- A guide to RACI with rules and common mistakes
- A governance structure with tiers, members and meeting rhythm
- A RACI matrix in PowerPoint
- An Excel RACI that checks every row automatically
Worked example
Three rows from the RACI, and the governance around them.
| Approve the AI for live use | Accountable: COO. Responsible: head of mortgage operations. Consulted: chief risk officer, data protection officer, compliance. Informed: brokers. |
|---|---|
| Change underwriting mandates | Accountable: chief credit officer. Responsible: head of underwriting. Consulted: risk, HR. |
| Release contingency over £100k | Accountable: the steering committee. Below £100k, the programme director decides. |
| Governance | A monthly steering committee chaired by the COO, a fortnightly design authority, and an AI risk review before every release. |
What happened next. When bank-statement accuracy fell short, everyone knew it was the steering committee's decision, and it was made in one meeting.
Preview
Questions
What does RACI stand for?
Responsible (does the work), Accountable (owns the outcome and signs off), Consulted (gives input before) and Informed (told after). Each activity should have exactly one A.
What is the most common RACI mistake?
Too many people marked Accountable or Consulted. Two As means nobody is accountable, and a row full of Cs slows every decision. The Excel version checks each row for you.
Rate and review
How useful was this template?
Your rating and comments help me improve the template and decide what to build next. It takes less than a minute.
Thank you.
Your feedback has been sent. If you have got another minute, share the template with someone who'd find it useful.